Action B.2 – Preparation of Implementation Scenarios

Proposed starting and end date of action: 01/02/13-01/08/13
Actual starting and expected end date of action: 01/02/13-01/08/13
Status: Completed

Description:

Based on the data collected in Action B.1, a number of scenarios for the use of waste quarry slurry in the clay brick/tile and cement industry were be prepared. These scenarios will make the basis on which the pilot implementation/ demonstration activity will be carried out in Action B.3.

Methods Employed:

Methods Employed:

Under this Action a number of scenarios for the use of waste quarry slurry in the clay brick/tile and cement industry were prepared, on which the demonstration action would be based for implementation. Initially, an assessment of the physical and chemical characteristics of the quarry slurry produced by LF was carried out by the project beneficiaries under the guidance of N&A. In addition, identification of the existing raw material to be replaced by the cement and clay brick/tile industries was investigated by the relevant industrial beneficiaries. Moreover, data were collected for the preliminary identification of CO2 emissions from each implementation scenario. Eventually CO2 emissions were estimated for each implementation scenario during Action B.2 in a theoretical level (based on assumptions and calculations made with theoretical values).

Results:

  • Preparation and presentation of a report presenting the final scenarios to be implemented. It expected that 15 scenarios will be prepared for the clay brick/tile industry and another 10 for the cement industry.
  • CO2 emission reduction levels for each scenario presented
  • Environment LIFE Programme
  • Department of Environment
  • Nicolaides and Associates Ltd
  • Latomia Pharmakas PLC
  • Vasiliko Cement Works
  • United Brickworks