Action Packages

The Work Plan of the project sets forth various components that need to be addressed in succession iteratively. The actions in the QuaResE project are therefore broken down into a number Action Packages, each focusing on a different type of work:

A. Preparatory actions

Action Number

Name of Action

Duration

A.1

Task Dissemination

(01/06/2012-20/10/2012)

A.2

Stakeholder Consultation

(02/10/2012-15/10/2012)

B. Implementation actions

Action Number

Name of Action

Duration

B.1

General Data Collection and Identification of Present Conditions

(02/07/2012-01/04/2013)

B.2

Preparation of Implementation Scenarios

(01/02/2013-01/08/2013)

B.3

Demonstration Action

(01/07/2013-01/05/2014)

 

C. Monitoring of the impact of the project actions

Action Number

Name of Action

Duration

C.1

Financial, Social and Environmental Assessment

(02/04/2014-30/09/2014)

C.2

Production of Industry Guides

(01/10/2014-30/11/2014)

 

D. Communication and dissemination actions

Action Number

Name of Action

Duration

D.1

Dissemination of Results

(01/06/2012-30/11/2014)

D.2

Networking

(01/01/2013-30/11/2014)

D.3

After Life Communication Plan

(01/11/2014-30/11/2014)

 

E. Project management and monitoring of the project progress

Action Number

Name of Action

Duration

E.1

Project Management and Reporting to EC

(01/06/2012-30/11/2014)

E.2

Project Monitoring

(01/06/2012-30/11/2014)

  • Environment LIFE Programme
  • Department of Environment
  • Nicolaides and Associates Ltd
  • Latomia Pharmakas PLC
  • Vasiliko Cement Works
  • United Brickworks